Greetings from site, week 39

3
.
10
.
2018
Edited
3
.
10
.
2018

Interior demolition work is almost complete in Accountor Tower.

Interior demolition work in Accountor Tower have almost been completed.However, there is still some ongoing demolition work in tower’s basementand top floors.

• Currently we’re building the foundations for tower crane in P3-parking floor,near old exit ramp. Due to tower crane we need to expand construction sitearea in northern side of the tower

• In floors 6-14, we’re already building a new and now we’re boarding, sealingand painting walls in office floors. We have also started to install a newbuilding service technic (heating, ventilation and air conditioning HVAC)

• There is also a new intermediate floor in third floor around the elevators

• Later in this autumn we will start demolition of old swimming hall andgymnasium at the eastern side of the tower. In addition, later we will beginto assemble scaffoldings around the tower. Scaffoldings are necessary forfacade washing and changing the windows.

Some pictures from construction site attached above.

MORE INFO

Joonas Rinkinen

Communications Coordinator, Keilaniemenranta

YIT Construction Ltd.

mob. 050 581 0737 or joonas.rinkinen@yit.fi